Construction Phase
  • Temporary wastewater treatment systems are installed for water generated from construction processes and water used during construction.
  • Water quality is monitored according to EIA requirements before discharge into public drainage systems.
Implementation Period
  • All projects install standard-compliant wastewater treatment systems and hand them over to the condominium management for ongoing operation, ensuring water quality control before discharge into public drainage systems.
  • Water samples are collected for quality testing monthly and reported to the relevant authorities.